Five-year housing land supply position statement (as at 01 April 2022)

Calculation of the five-year housing land supply position

Tables 2 and 3 summarise the sources of supply for the five-year period (2022 to 2027) and the total number of years of deliverable housing land. A full breakdown of each individual site assessed within this position statement can be accessed below: 

Table 2: Summary table of sources of deliverable housing supply 2022 to 2027
Sources of supply2022-232023-242024-252025-262026-27
Major sites (sites of 10 or more dwellings, or 0.5ha or more) with full or detailed planning consent43727123424192
Small sites (sites below 10 dwellings or 0.5ha) with planning consent (full/outline)101202954621
Allocations (Local Plan)0025138193
Major sites (sites of 10 or more dwellings or 0.5ha or more) with outline planning consent103025180109
Windfall00255098
Subtotals548503404655513
Grand total (2022-23 to 2026-27)2,623
Table 3: Number of houses and years identified against the five-year requirement
Calculation codesFive-year housing land supply componentNumber of dwellings
AFive-year supply requirement including 10% buffer1,810
BAnnual requirement (A divided by 5)362
CTotal number of units identified2,623
DNumber of units above or below five-year supply requirement (C minus A)813
ENumber of years of deliverable housing land (C divided by B)7.24

Results summary

This position statement has identified sites within the borough of Great Yarmouth that are capable of delivering 2,623 new homes within the next five-year period (April 2022 to March 2027). The target requirement over this period is 1,810 therefore this represents an over provision of 813 new homes.

In conclusion, this statement identifies sites capable of delivering 7.24 years of housing land supply.

Last modified on 27 July 2023